The existing site blowers are aged and require replacement due to difficulty obtaining spares, and there being more efficient technology on the market.
The existing sub-terranean pipework is in poor condition and there are numerous large leaks that become evident when it rains - this is estimated to cost around £x,xxx annually in wasted air.
The project consists of civils work to enable the installation of a new distribution system with access to the lanes, new pipework, and new blowers.
The civils work is now largely completed and we're waiting for the concrete to cure before we can install the large bore pipework in the new year.